Western General Hospital, Edinburgh
New Oncology Unit
Client: Western General Hospital
Tender Value: £1,100,000.00
Programme: 55 Weeks
This was as 55-week Project, split into 3 Phases, with the addition of an
overall Ventilation, Heating and Water Services Upgrade to the East Suite.
Phase 1 consisted of a 16-week programme to refurbish the ground floor of the
East Suite to provide reception/control desk areas for 2 radiation treatment
rooms, patient waiting room, toilets and consulting rooms etc. We were required
to maintain the operation of the department whilst the works were carried
out.
Phase 2 consisted of a 26-week programme involving major modifications to a
treatment room in the West Suite to allow the installation of a new treatment
machine. The work also included the upgrading of structural walls to provide
additional radiation protection.
Phase 3, like the previous phase, consisted of a 13-week programme involving
major modifications to one of the treatment rooms in the East Suite to allow the
installation by others of a new treatment machine.
This work was completed on time and on budget.